Reconstruction in S. Zvonkovo
Object DesignThe room is intended for the heat supply of the building of a living room for students on the vol.Resurrection in S.Dzvinkovo, Vasilkovsky district of the Kiev region.Size: 8x7,17x3,4(h) mExternal air parameters:
Calculatory external temperature of burning - -22 ° C;
Calculating external temperature for ventilation - +20 ° C;
The average temperature of the outside air for the burning period is -0,1 ° C.The duration of the burning period is 176 days.For the coverage of the thermal loads, the installation is provided in
… Two-Pilot Coaters BRS 100 Comfort
LM and BRS 150 Comfort Manufacturing Company "Korostan Burning Factory"
Techniques" (Ukraine), which work on wood and pellets.Nominal Power
Coats: 99,0 kW and 150 kW.Coefficient of beneficial action of cottles - 84% for burned trees and
92% of the work on pellets.The total thermal productivity of the ball is 250 kW (0,2149 Gcal/hour).The thermal scheme requires the preparation of a thermal carriage - water with a temperature of 90-70 ° C.The project provides automatic weather-related temperature regulation
Network water contour of the combustion system using automatic control
External temperature and temperature sensor (seeThe ATM Division.The project provides for the installation of calculation devices:
Cold water (calculator) for the heat supply system;
- Heat energy (computor) with two uterus (on the supply and reverse)
the pipeline).
-
Building of the Emergency Brigade Support Point
Object DesignThe project facility is intended for the heat supply of the emergency bridges of the PAT branch in the Dniprovsky district.by Kiev.Size of room 7.32x4.2x2.5(h) m.External temperature for heating and ventilation - -22 ° C;
The average temperature of the outside air for the burning period is -0,1 ̊C.The duration of the burning period is 176 days.For the coverage of heat loads, the installation in the premises of the automated boiler "Logamax plus" GB 162-100 V2 of production by the company "Buderus" (Germany), working on natural gas of low pressure and the heat pump "Octopus" "air-water" IS81 with a heat power of 25 kW.The nominal capacity of the cottage: 94.5 kW (0.0812 Gcal/hour).The coefficient of the beneficial effect of the coat when working on natural gas is 97,0%.Thermal - water with a temperature of 60-40 ° C.The project provides automatic weather-related regulation of the temperature of the direct grid water.The preparation of hot water is provided for the home of the vertical air heater Logalux SU750 with a capacity of 750 liters.The structure of the side allows it to be further equipped with electric shade for water heating.The control of the hot water supply system will be carried out in automatic mode (see.The ATM Division.This functional module allows you to control the work of the circulation pump (position K10).And the work of the circulatory pump will be performed according to the timer work program (work with interruptions or constant).The module is equipped with the function of "thermal disinfection" of the GDP contour, which performs heating hot water once a week to the temperature needed to destroy the legionel (the trigger of respiratory tract diseases).Thermal disinfection should be carried out only at night time in order to avoid humans smoking with water.
-
Warming, ventilation and air conditioning of the apartment
Object DesignHeating, ventilation and air conditioning in the apartment. Mr. Irpine, Vol. The Northern
-
Recovery of the thermal security of the DNZ in M. Lviv
Object DesignRecovery of the Pre-School Heat Insurance System
No. 14 is located at the address: m.Levi and Vol.Newly completed in
compliance with the design task and with current rules and rules.The main source of heat supply of the combustion system is the electric coat,
The Protherm Scat.1 .The water burning system is a two-train horizontal fool (75/55 ° C).The circulation of heat in the heating system is provided by the pumps that
… Installed in the cottage on the coal floor.Burning devices on the coal floor are registers of smooth tubes.The 2ndThe pipelines of the combustion system are performed from polypropylene.As a combustion device, the project provides aluminum sectional radiators of type
"Calidor" production of f-mi "Fondital" (side connection) with the Crane of the type of Mayevsky.Radiators are supplied in painted and in collected form at the manufacturer's factory.3 .The regulation of the combustion system is qualitative.in the regulation.
This is due to the temperature change of heat, and
Installation in the equipment that is equipped
Thermostatic valves with thermal leaves of manufacturing firm "Danfos"..
-
Reconstruction of private housing in you
Object DesignThe following technical decisions are made:
1 .The cabin is placed on the bottom.0,000 and designed for
Heat supply of individual housing by vol.The cover,
in m.Kiev, the Kiev region.2.The heat load is covered by the installation of the condensation boiler
… GB112-60, power of 60 kW of Buderus firm and heat pump "air-water"
OCHSNER Golf Maxi Plus with a power of 16 kW (at +7/35).The Inverter Type.In the development of the project, the constructive sizes and technical characteristics of the equipment
by the manufacturer’s creation,
3 .Removal of smoke gases and dissolving harmful substances into the atmosphere
It is carried out by a coaxial smoke tube Ø80/125 with a height of 10 m from PP plastic.The heat supply system is closed double.Temperature schedule of heat release for consumers on need : heating 55/50 C, heat
floor 50/45 ° C, ventilation 60/40 ° C and EEA 70/55 ° C.The hot water supply system is water with a temperature of 50 ° C.and 5.In the cabin is provided natural flow-output ventilation from the calculation
Air supply for burning and constant 3-fold wind exchange.6 .Heat and heat points are automated, scheduled for work without constant
the service staff.7 .The pipes are made from the REHAU type RAUTITAN flex pipes.8thThe horizontal parts of the pipelines are placed with a inclination of not less than 0.002.
The 9.In the top points of the pipelines to predict the aircraft.10 Pipelines are subject to hydraulic testing at pressure 1.25 from the worker, after which
They are isolated by heat-isolating materials.
-
Reconstruction of the wooden burning system
Object DesignReconstruction of the burning system of the building of the wooden processing facility of the NUBIP of Ukraine "Boyarskaya forest research station" in Boyarka, vol. The Forest, 12
Reviews and compliments on completed projects 2
11 March 2025
49 USD
Development of engineering networks in a 140m2 house
Quality
Professionalism
Cost
Contactability
Deadlines
The performer is qualified, punctual, always in touch. I will continue to work with him. I recommend.
18 February 2020
68 USD
Making CTP pipeline dissolving in 3D in AutoCAD / Revit
Quality
Professionalism
Cost
Contactability
Deadlines
The work is done very professionally, at a high level.
Activity
| Latest proposals 10 | Budget | Added | Deadlines | Proposal | |
|---|---|---|---|---|---|
|
Development of a modular boiler house
451 USD
|
|||||
|
Thermal engineering design
226 USD
|
|||||
|
Development of a water supply and sewage plan for a residential building
68 USD
|
|||||
|
Development of engineering networks in a 140m2 house
49 USD
|
|||||
|
Scary intentions of construction
113 USD
|
|||||
|
Heat floor building
23 USD
|
|||||
|
Scheme of heat floor discharge by infusion
14 USD
|
|||||
|
Projects of private house 200m2
23 USD
|
|||||
|
Translation of drawings into dwg format
11 USD
|
|||||
|
Проект канализационных закладных в фундамент
54 USD
|