Start of design - September 2006
Construction completion - May 2007
Before the reconstruction:
1 . The number of numbers is 18.
2nd Construction volume is 1255.74 cubic meters.
Three The calculation capacity is 95.77*2/4=48 cells.
After the reconstruction:
1 . Number of numbers is 36.
2nd Construction volume is 3996.72 cubic meters.
Three Capacity of calculation: 137
The reconstruction and expansion of the existing morally aged bedroom is completed, the re-planning of the existing floors, the rebuilding of the 2nd floors.
In order to solve the problem of building upgrade without increasing the burden on existing stable foundations, a constructive scheme has been adopted, allowing the burden to be transferred from new structures to separate foundations.
For the building, a constructive scheme is adopted in the form of a metal frame with filling of pen-beton small blocks.
Monolithic iron-beton percrete in an immeasurable column of profiled steel leaf.